project description

An ambitious collaboration with SOGEA CARONI with no less than 48 housing units.
Smart Cast was commissioned to design the electrical layout as well as that of the plumbing.
Once validated, we produced the custom-made electric and hydraulic octopuses and delivered to the site.
The Sogea Caroni company installed the panels as well as the networks on their own thanks to the Smart Cast process designed to facilitate the work of incorporation into the slab.
• Delivery of pre-wired electric octopuses
• Marking of marks and drilling of plates for the passage of the electricity ducts in the factory
• Delivery of pre-cased and pre-assembled hydraulic octopuses
• Tracing of the plumbing duct routes and drilling of the plates in the factory to facilitate the descent into the partition
• Help with the first installation on site
• Telephone support
• A single point of contact for ELEC, PLUMBING and PLATES studies
Start of work in early June 2020, last delivery at the end of September 2020.

I have a similar project

technical informations

Partner :
Number of housings : 48
Type : Lodging
Floor area : 2610 m2
Technical solutions : Smart Cast panel electrical and plumbing prefabrication